Mercator Minerals Ltd. is pleased to provide an update on activities at its wholly owned El Pilar project. On January 12, 2012, the Company’s subsidiary which holds the El Pilar project, made the final payment for the change of land use permit which allows mining to commence. Also, over the past few months, the final water concessions have been obtained, which along with the previously granted mineral concessions, surface rights, and construction permit, allows for the commencement of construction and mining operations at the El Pilar project. Detailed engineering, environmental studies and right of way on the power transmission line and access road have also been advanced. Detailed engineering work continues with major equipment sourcing and construction bid materials being prepared.