VANCOUVER, BRITISH COLUMBIA–(Marketwire –
First Quarter 2012 Financial and Operating Highlights:
- Gold production in the first quarter of 2012 increased 10% to 37,587 ounces from 34,169 ounces in the first quarter of 2011;
- On-site average cash cost1 per ounce of gold produced of
$1,758 in the first quarter of 2012. High production costs were primarily a result of the structural failure of the crusher feed bin which resulted in theSao Francisco Mine not having use of its primary crusher for 47 days, a$13.4 million production inventory write-down, as well as lower than normal production atSan Andres due to the changeover of mine contractors. Production and cash costs and are comprised of the following:
For the three months | For the three months | |||||
ended March 31, 2012 | ended March 31, 2011 | |||||
Ounces Produced | Cash Costs1 | Ounces Produced | Cash Costs1 | |||
San Andres Mine | 13,386 | $ | 1,130 | 18,125 | $ | 626 |
Sao Francisco Mine | 15,349 | 2,424 | 7,188 | 811 | ||
Sao Vicente Mine | 8,852 | 1,553 | 8,856 | 1,464 | ||
Total / Average | 37,587 | $ | 1,758 | 34,169 | $ | 882 |
1 See cautionary note regarding non-GAAP measures. |
- Copper production at the
Aranzazu Mine for the first quarter of 2012 of 3,345,500 pounds, which is a 255% increase over the first quarter of 2011 and 17% higher than the fourth quarter of 2011; - Revenue of
$75.6 million in the first quarter of 2012, an increase of 41% over the first quarter of 2011, and comprising net gold sales of$61.6 million (2011 –$51.6 million ) from 37,226 ounces (2011 – 37,512 ounces) and$14.0 million (2011 –$2.2 million ) from the shipment of 5,396 dry metric tonnes (“DMT”) (2011 – 873 DMT) of copper concentrate; - On-site average cash cost1 per pound of payable copper produced, net of gold and silver credits, of
$2.46 for the first quarter of 2012 compared to$4.87 for the first quarter of 2011. Although first quarter cash cost1 per pound of payable copper produced are only marginally higher than the fourth quarter cash cost1 of$2.32 , the positive effect of increasing production levels during the first quarter was offset by the adverse effect of elevated arsenic levels in theAranzazu Mine’s concentrate production, which are included in cash costs1; - Loss for the first quarter of 2012 of
$18.7 million or$0.08 per share compared to a profit of$4.4 million or$0.02 per share for the first quarter of 2011; - Ended the first quarter of 2012 with
$13.9 million in cash and cash equivalents and$5 million available under the$25 million revolving credit facility (“Credit Facility”), which was drawn down inApril 2012 . OnMay 10, 2012 , the Company amended the Credit Facility, extending the maturity toJune 30, 2014 and increasing the credit available to$45 million ; - In connection with the implementation of the new mine plans at the Brazilian Mines, the Company established a gold hedge program covering a total of 80,000 ounces of gold between
April 1, 2012 andJune 30, 2014 , using zero-cost put/call collars with a floor price of$1,700 per ounce of gold and an average ceiling price of$1,812 per ounce of gold; - Continued to progress and optimize the bankable feasibility study for the
Serrote Project , which is scheduled for completion in the third quarter of 2012; and - Continued work on the Preliminary Economic Assessment for the Aranzazu expansion project, which is scheduled for completion by the end of the second quarter of 2012.
“As mentioned in our 2011 year-end operational results, the first quarter was negatively affected first, by an extended primary crusher outage at Sao Francisco and second, by higher than expected levels of arsenic at the
Largely because of the non-recurring outage at Sao Francisco, the Company’s cash flow was negative for the quarter and the Company’s cash balance decreased by approximately
Going forward, the business plan remains unchanged. We expect to realize significant cash flows from the Brazilian mines over the next three years to be reinvested in the expansion of
Financial Review
The following financial information does not constitute management’s discussion and analysis (“MD&A”) as contemplated by relevant securities rules and should be read in conjunction with the Company’s unaudited condensed interim consolidated financial statements for the three months ended
The following table presents a summary of financial information for the three months ended
(In thousands of dollars, | Three months ended | Three months ended | |||
except per share amounts) | March 31, 2012 | March 31, 2011 | |||
(Unaudited) | (Unaudited) | ||||
Revenue | $ | 75,596 | $ | 53,789 | |
Cost of goods sold | (86,128) | (51,519) | |||
Gross Margin | (10,532) | 2,270 | |||
Expenses | |||||
Exploration expenses | (3,865) | (3,893) | |||
General and administrative expenses | (6,268) | (6,969) | |||
Finance costs | (872) | (1,289) | |||
Interest and other (expense) income | (19) | 165 | |||
Gain on restructuring of contractual obligations | – | 17,009 | |||
Other gains | 4,913 | 829 | |||
(Loss) profit before income taxes | (16,643) | 8,122 | |||
Income tax expense, net | (2,040) | (3,759) | |||
(Loss) profit for the period | $ | (18,683) | $ | 4,363 | |
Basic and diluted (loss) profit per share | (0.08) | 0.02 |
1 See cautionary note regarding non-GAAP measures.
Gold ounces sold for the respective periods, the average realized prices per ounce and net sales are detailed in the following table. The average realized prices per ounce for the three months ended
Three months ended | Three months ended | |||
March 31, 2012 | March 31, 2011 | |||
San Andes Mine, (ounces) | 12,678 | 18,464 | ||
Sao Francisco Mine, (ounces) | 15,492 | 9,082 | ||
Sao Vicente Mine, (ounces) | 9,056 | 9,966 | ||
Total ounces sold during Quarter | 37,226 | 37,512 | ||
Realized average gold price per ounce in Quarter | $ | 1,691 | $ | 1,388 |
Gold sales revenues (in ‘000’s) net of local sales taxes | $ | 61,618 | $ | 51,566 |
Copper concentrate sales (in ‘000’s) | 13,978 | 2,223 | ||
Total net sales (in ‘000’s) | $ | 75,596 | $ | 53,789 |
Copper concentrate sales in the table below comprised shipments for the three months ended
Three months ended | Three months ended | |||
(In thousands of dollars) | March 31, 2012 | March 31, 2011 | ||
Copper revenue, net of treatment and refining charges | $ | 8,922 | $ | 2,205 |
Gold by-product revenue | 3,154 | 640 | ||
Silver by-product revenue | 1,352 | 422 | ||
Price adjustments recorded | 550 | (57) | ||
Total revenue | $ | 13,978 | $ | 3,210 |
Less: pre-production revenue applied against property, plant and | – | (987) | ||
Total revenue recorded in the statement of income | $ | 13,978 | $ | 2,223 |
For the quarters ended
Other expense items for the first quarter of 2012 include general and administrative expenses of
For the first quarter of 2012, the Company recorded finance costs of
For the first quarter of 2012 and 2011, the Company recorded a net loss of
Liquidity and Capital Resources
As at
During the quarter ended
Operational and Project Review
The table below sets out selected operating information for the
San Andres Mine | ||||
Operating Information | Q1 2012 | Q1 2011 | ||
Ore mined (tonnes) | 1,088,600 | 1,313,100 | ||
Waste mined (tonnes) | 672,900 | 286,300 | ||
Total mined (tonnes) | 1,761,500 | 1,599,400 | ||
Waste to ore ratio | 0.62 | 0.22 | ||
Ore plant feed (tonnes) | 1,066,100 | 1,317,000 | ||
Grade (g/tonne) | 0.68 | 0.79 | ||
Production (ounces) | 13,386 | 18,125 | ||
Sales (ounces) | 12,678 | 18,464 | ||
Average cash cost per ounce of gold produced1 | $ | 1,130 | $ | 626 |
1 See cautionary note regarding non-GAAP measures. |
Operations continue to be affected by the processing of lower-recovery mixed ore having a higher component of clay alteration. This has resulted in lower ore movement from the mine, and downtime associated with the processing of wet ore and cleaning of chutes, as well as, poor contractor performance. The Company has taken several mitigating steps to improve production, including replacing the primary crusher wobbler during the first quarter of 2012 with a vibrating grizzly screen ahead of the jaw crusher to improve plant operating time, throughput and efficiency. Starting in
Gold production at the
Operating cash costs1 of
1 See a cautionary note regarding non-GAAP measures.
The table below sets out selected operating information for the
Sao Francisco Mine | ||||
Operating Information | Q1 2012 | Q1 2011 | ||
Ore mined (tonnes) | 817,600 | 65,900 | ||
Waste mined (tonnes) | 3,921,500 | 5,279,700 | ||
Total mined (tonnes) | 4,739,100 | 5,345,600 | ||
Waste to ore ratio2 | 4.80 | 80.12 | ||
Ore plant feed (tonnes) | 1,070,200 | 26,900 | ||
Grade (g/tonne) | 0.63 | 0.38 | ||
Production (ounces) | 15,349 | 7,188 | ||
Sales (ounces) | 15,492 | 9,082 | ||
Average cash cost per ounce of gold produced1 | $ | 2,424 | $ | 811 |
1 See cautionary note regarding non-GAAP measures. |
2 Includes deferred stripping waste. |
First quarter 2011 results in the table above are not comparable to the first quarter 2012, as the 2011 period was impacted by the dedicated waste stripping program which was undertaken from early
First quarter 2012 operations were impacted by the failure of the main shaft bearing in the jaw of the primary crusher in late-November, which was down for approximately two weeks before a rental crusher was installed. Although smaller than the primary crusher, the rental crusher made up a sizable percentage of the otherwise lost throughput, albeit at a higher cost. Significant preventive maintenance was completed in the tertiary crusher and gravity circuits during this period. First quarter 2012 was also impacted by a structural failure of the primary crusher feed bin in early February, which resulted in the operation not having use of the primary crusher for 47 days. The structural issues were rectified and the repaired crusher was re-installed in
Average cash costs1 of gold produced during the quarter were
1 See cautionary note regarding non-GAAP measures.
The table below sets out selected operating information for the
Sao Vicente Mine | ||||
Operating Information | Q1 2012 | Q1 2011 | ||
Ore mined (tonnes) | 304,200 | 801,800 | ||
Waste mined (tonnes) | 987,900 | 1,585,800 | ||
Total mined (tonnes) | 1,292,100 | 2,387,600 | ||
Waste to ore ratio2 | 3.25 | 1.98 | ||
Ore plant feed (tonnes) | 500,200 | 784,700 | ||
Grade (g/tonne) | 0.69 | 0.47 | ||
Production (ounces) | 8,852 | 8,856 | ||
Sales (ounces) | 9,056 | 9,966 | ||
Average cash cost per ounce of gold produced1 | $ | 1,553 | $ | 1,464 |
1 See cautionary note regarding non-GAAP measures. |
2 Includes deferred stripping waste. |
The average cash cost1 per ounce produced in the first quarter of 2012 was
1 See cautionary note regarding non-GAAP measures.
The table below sets out selected operating information for the
Aranzazu Mine | |||||
Operating Information | Q1 2012 | Q1 2011 | |||
Ore mined (tonnes) | 233,900 | 105,600 | |||
Ore milled (tonnes) | 192,600 | 126,100 | |||
Copper grade (%) | 1.01% | 0.74% | |||
Gold grade (g/tonne) | 0.55 | 0.30 | |||
Silver grade (g/tonne) | 11.16 | 15.78 | |||
Copper recovery1 | 77.6% | 46.2% | |||
Gold recovery | 70.1% | 50.7% | |||
Silver recovery | 67.7% | 49.1% | |||
Concentrate production: | |||||
Copper concentrate produced (dry metric tonnes (“DMT”)) | 6,183 | 1,728 | |||
Copper contained in concentrate (%) | 24.5% | 24.8% | |||
Gold contained in concentrate (g/DMT) | 11.5 | 12.4 | |||
Silver contained in concentrate (g/DMT) | 251.2 | 538.8 | |||
Copper contained in concentrate (pounds) | 3,345,500 | 942,900 | |||
Estimated payable copper produced (pounds) | 3,175,600 | 892,700 | |||
Estimated payable gold produced (ounces) | 2,087 | 601 | |||
Estimated payable silver produced (ounces) | 43,892 | 27,023 | |||
Average cash cost per payable pound of copper produced,net of gold and silver credits 2,3 | $ | 2.46 | $ | 4.87 |
1 Recoveries based on a mixture of sulphide and oxide ores, not primary sulphide ores. |
2 See cautionary note regarding non-GAAP measures. |
3 For post commissioning period, starting February 1, 2011. |
First quarter 2011 results in the table above are not comparable to the first quarter 2012, as the operation experienced several operational and maintenance issues during and following declaration of commercial production. Production during 2011 was also impacted by the mining of a higher than planned proportion of oxidized ore from the open-pits and previously stockpiled ores which reduced mill recoveries.
During the first quarter of 2012, underground mining continued to be ramped up with the mining of ore from the high grade BW and AA Zones. Improvements in the mine continue with better equipment availability through the hiring of an experienced Maintenance Manager. Additionally, improvements in power and water supply, which affected the fourth quarter of 2011, were rectified and enabled higher first quarter mill throughput to be achieved. Nonetheless, the operation experienced a one week outage of the tertiary crusher during the quarter, leading to lost production for those seven days and consequent effect on quarterly production and costs.
The average head grades of the ore processed during the first quarter of 2012 were, with the exception of silver grades, considerably higher than the first quarter of 2011, and consistent with grades mined and processed in the fourth quarter of 2011. First quarter 2012 recoveries increased for all payable metals, particularly silver and gold, from the prior quarter, and were also substantially higher than recoveries in early 2011. These increases were due to a reduced oxide component in the ore, higher head grades, and stable operating conditions in the process plant. This trend is expected to continue. As a result, the
During the quarter ended
Cash costs1 per payable pound of copper for the first quarter 2012 were
The Company continues evaluating increased production levels at the
Outlook and Strategy
Other key factors influencing profitability and operating cash flows are production levels – impacted by grades, ore quantities, labour, plant and equipment availabilities, and process recoveries – and production and processing costs – which are impacted by production levels, prices and usage of key consumables, labour, inflation, and exchange rates.
Gold Mines – Production Estimates | ||
San Andres Mine | $1,000 – $1,100 | 60,000 – 65,000 oz |
Sao Francisco Mine | $1,500 – $1,700* | 70,000 – 80,000 oz |
Sao Vicente Mine | $1,100 – $1,200 | 35,000 – 40,000 oz |
Total | $1,250 to $1,400 | 165,000-185,000 oz |
* Full year 2012 cost estimate includes first quarter impact of failure in primary jaw crusher, the structural failure of primary crusher feed bin, and the write-down to net realizable value of production inventory at the Sao Francisco Mine. |
As previously guided, operating cash costs1 per ounce for the
The one-time impact of the failed jaw crusher bearing and the structural failure of the feed bin in the first quarter of 2012, combined with the mining and processing of lower grade ore material during the first and second quarters of 2012, will adversely impact production and increase cash costs1 in the first half of 2012. However, in accordance with the new business and mine plan for this operation, cash costs1 are expected to decrease in the second half of 2012 and further decrease in subsequent years as progressively higher grade ore material is mined as the pit deepens, and as strip ratios are reduced. As a result, the Company expects cash costs1 for the
Operating cash costs1 per ounce for the
The Company’s 2012 production guidance for the
Aranzazu Mine – Production Estimates | |
Copper | 13,000,000 – 14,000,000 lbs |
Gold | 7,500 – 8,500 oz |
Silver | 145,000 – 155,000 oz |
Cash costs1 per payable pound of copper for the
Total capital expenditure guidance for the balance of 2012 is approximately
The Company’s primary strategic focus for 2012 and beyond remains unchanged, and includes: improving operational efficiencies at the
1 See cautionary note regarding non-GAAP measures.
Conference Call
The call is being webcast and can be accessed at
Non-GAAP Measures
This news release includes certain non-GAAP performance measures, in particular, the total cash costs of gold per ounce and cash costs per payable pound of copper. These non-GAAP measures do not have any standardized meaning within International Financial Reporting Standards (IFRS) and therefore may not be comparable to similar measures presented by other companies. The Company believes that this information is useful to management and certain investors in evaluating the Company’s performance. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Cash costs are presented as they represent an industry standard method of comparing certain costs on a per unit basis. Total cash costs include on-site mining, processing and, administration costs, off-site refining and royalty charges, reduced by by-product credits, but exclude amortization, reclamation, and exploration costs, as well as capital expenditures. Total cash costs are divided by ounces to arrive at per ounce cash costs. Similarly, total cash costs of copper produced include the above costs, and are net of gold and silver by-products, but include offsite treatment and refining charges. Total cash costs of copper produced are divided by payable pounds of copper produced to arrive at per payable pound cash costs.
About
Cautionary Note Regarding Forward-Looking Statement:
This document contains “forward-looking information” within the meaning of Canadian securities legislation and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995. This information and these statements, referred to herein as “forward- looking statements” are made as of the date of this news release or as of the effective date of information described in this news release, as applicable. Forward-looking statements relate to future events or future performance and reflect current estimates, predictions, expectations or beliefs regarding future events and include, without limitation, statements with respect to: (i) the amount of mineral reserves and mineral resources; (ii) the amount of future production over any period; (iii) the amount of waste tonnes mined; (iv) the amount of mining and haulage costs; (v) cash costs; (vi) operating costs; (vii) strip ratios and mining rates; (viii) expected grades and ounces of metals and minerals; (ix) expected processing recoveries; (x) expected time frames; (xi) prices of metals and minerals; (xii) mine life; and (xiii) anticipated gold hedge programs. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as “expects”, “anticipates”, “plans”, “projects”, “estimates”, “envisages”, “assumes”, “intends”, “strategy”, “goals”, “objectives” or variations thereof or stating that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.
All forward-looking statements are based on the Company’s or its consultants’ current beliefs as well as various assumptions made by and information currently available to them. These assumptions include, without limitation: (i) the presence of and continuity of metals at the Brazilian Mines at modeled grades; (ii) the capacities of various machinery and equipment; (iii) the availability of personnel, machinery and equipment at estimated prices; (iv) exchange rates; (v) metals and minerals sales prices; (vi) appropriate discount rates; (vii) tax rates and royalty rates applicable to the mining operations; (viii) cash costs; (ix) anticipated mining losses and dilution; (x) metals recovery rates, (xi) reasonable contingency requirements; and (xiii) receipt of regulatory approvals on acceptable terms. Although management considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect. Many forward-looking statements are made assuming the correctness of other forward looking statements, such as statements of net present value and internal rate of return, which are based on most of the other forward-looking statements and assumptions herein. The cost information is also prepared using current values, but the time for incurring the costs will be in the future and it is assumed costs will remain stable over the relevant period.
By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates assumptions and intentions expressed in such forward-looking statements. These risk factors may be generally stated as the risk that the assumptions and estimates expressed above do not occur, but specifically include, without limitation, risks relating to variations in the mineral content within the material identified as mineral reserves and mineral resources from that predicted, changes in development or mining plans due to changes in logistical, technical or other factors, the impact of general business and economic conditions, global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future conditions, fluctuating metal prices (such as gold, copper, silver, nickel and iron ore), currency exchange rates (such as the Canadian dollar, Brazilian Real, Mexican Peso and the Honduran Lempira versus
When relying on our forward-looking statements, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. The Company does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by the Company or on behalf of the Company, except as required by law.
The forward-looking statements contained herein is presented for the purpose of assisting investors in understanding the Company’s expected financial and operational performance and results as at and for the periods ended on the dates presented in the Company’s plans and objectives and may not be appropriate for other purposes. The reader is also cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability.