SilverCrest Completes Second Tranche Drawdown of its Credit Facility for US$30 million
The funds will be used towards the continued construction of the Company’s Las Chispas Project located in Sonora, Mexico. At the end of H1, 2021, Las Chispas construction progress was at 33% compared to a scheduled completion of 28% and the Company anticipates reaching approximately 80% completion of construction by the end of 2021.