Fred Stanford, President & CEO of Torex stated: “280,000 ounces of gold in the first year of the ramp up, speaks to the quality of the deposit, the constructed asset, and the skill of the team in navigating through the technical and social start-up challenges. The ramp-up is expected to be completed during 2017, as solutions are in hand for the two remaining material technical issues. Construction is underway on the SART plant to manage the soluble copper and a decision has been made to increase tailings filtration capacity.” He added, “2017 will also be an exciting year from a development perspective as step-out drilling on the Sub-Sill discovery is planned and delivered, a resource estimate is prepared, and access is completed to allow material from this zone to be processed before year end. Media Luna is also poised to take a major step forward in 2017 with permits expected for an access ramp that we intend to start developing before year end. It promises to be an interesting year as we complete the ramp up of ELG and prepare the Company for the next stage of growth.”