“We increased production levels in the second quarter and we are committed on continuing to bring both of our mines up to their optimal operating rates,” stated Ernest Mast, President and Chief Executive Officer. “San Dimas showed solid production improvements over Q1 2016, achieving average mining rates of 2,500 tonnes per day. But there is still much work to be done to optimize and refine the mining cycle, increase development rates and maximize productivity and grades. We had labour disruptions during July that impacted July’s production and delayed some development work. As a result we initiated a mine optimization plan focusing on technical and human resources issues. We are continuing to make progress at Black Fox in developing the Deep Central Zone ahead of production expected in the third-quarter, unfortunately we have experienced delays in early July due to poor ground conditions on the 660 metre level. In light of these challenges the Company has reduced its 2016 production guidance.”